Social Work homework help. 1. Create a finished goods production plan MRP (and component B procurement plan) given the following:o Production cycle time = 1 montho Each finished good item requires 2 Part Bs; part B has a 1 month procurement lead timeo Beginning finished product inventory is 1,000o Forecasted sales are as follows:§ Month 1: 1,000§ Month 2: 1,100§ Month 3: 1,150§ Month 4: 1,200§ Month 5: 1,200§ Month 6: 1,300o Safety Stock: On the first day of each month, you want to have that month’s sales already in inventoryo Capacity of the plant is 1,300 units